Architect’s Guide to Building Renovation & Tenant Improvements
Typical Timeline
Site Selection
Broker research to identify potential locations/properties for sale
Tour sites w/ Architect
Purchase
Real Estate Attorney prepare/review Purchase & Sale Agreement (PSA)
Purchase Due Diligence
Property Survey by Civil Engineer (check for encroachments and easements) + Topography
Soils Testing by Geotechnical Engineer (required for structural engineering)
Architect to research City Planning and Zoning codes to determine New Building envelope (F.A.R.,
[floor area ratio – max size of residence] Height and Set-back requirements).
Determine if any Neighborhood Associations or CCR’s (covenants, conditions, or restrictions) exist
Professionals and Fee Structure
Architect – initial design fee, then once scope is determined prepare a contract - percentage
cost of construction or fixed fee
Professional Engineers and Consultants – cost per sq. ft. or fixed fee
[Surveyor – Soils, Civil, Structural, Mechanical, Electrical & Plumbing Engineers]
[Interior Designer, Lighting Designer and Landscape Architect]
Land Use Consultant – expediate entitlements and permits – fixed fee
Project Manager /Owner’s Rep – consultant to help manage the project – monthly fixed fee
Architect Design and Development
Programming
Develop list of need, number, and size of spaces/rooms – “wish list”
Special requirements – screening rms, gyms, office, meditation room
Amenities – lounge, chef’s kitchen, play areas – pool/spa, tennis/rack ball court
Architect to prepare overall project schedule
Conceptual Design
Architect inspiration sketches
Site and Space plans (simple floor plans) – Potential Different Versions
Discuss over all look and feel
Schematic Design and ROM Budget
Floor plans, 3D building renderings and suggested materials palette
Notes and specs for initial construction budget by General Contractor
Design Development
Further building design – Physical Scale Model and interior/exterior 3D renderings
Proposals / Engage Consultants & Engineers
Prepare Initial set of plans coordinated with design team for Design Review
City Planning and Architectural Review Board – Architect to prepare documents
All new buildings need approval by City Planning to make sure they comply with Zoning requirements.
Santa Monica has the Architectural Review Board that includes a public hearing for
approval (presently done administratively due to C19)
Construction Documents & Permits
Architectural plans and engineering for building department submittal
Selection of finish materials, lighting/plumbing fixtures and built-in furniture
Contractor Bidding – Building Permits
Interview or Pre-qualify General Contractors
Bid plans during plan check submittal
Plan Check Corrections
Respond and coordinate city comments back to design team
Re-submit corrected plans. Possible second round corrections.
Value Engineering
Review bids to see what design changes are acceptable to lower price but keep intent
Construction Contracts
Negotiate Fixed Price or Cost Plus a Fee Contract based on final city comments
and value engineering construction documents
“Critical Path” Project Schedule provided by Contractor
Construction Phase
Weekly conference calls and/or site meetings
RFI’s (request for information issued by GC to architect)
Change orders – plus or minus
Submittals issued by GC to architect for final approval (plumbing & light fixtures,
materials, hardware, finishes)
Pay applications – Architect to review and certify work completed (necessary for bank loans)
Completion
Fixtures and finishes
Install Furniture
Final Landscaping
C of O and/or Occupancy
Punch list
Close out and Warranties